Epoxy resin flat coating floor paint construction plan process
Release time:2018-09-15
Epoxy floor paint construction scheme
1. Construction process
1.0mm thick epoxy floor paint construction process:
Base surface grinding, cleaning, crack repairing → painting epoxy sealing primer 1 time → painting epoxy intermediate paint 1 time → painting epoxy floor topcoat 1 time, the bottom, middle and top paints are required to be painted once a day .
Second, the construction method:
1. Base surface treatment:
A. Cleaning and inspection of the substrate: After cleaning or vacuuming the substrate, inspect the substrate for cracks and empty shells. If there is, it must be deeply cut and cleaned and filled with epoxy resin mortar. Do not beat violently during cleaning to avoid knocking loose edges. upper base.
2. Primer ratio: Primer A component: Primer B component (1:1), before construction, firstly stir primer A and primer B respectively, then mix them in proportion, and stir thoroughly for 3~5 Minutes, it can be constructed and needs to be used within 60 minutes.
3. The ratio of topcoat: paint: curing agent (4:1), before construction, fully stir the paint for 2~3 minutes, and then mix it with the curing agent according to the proportion, and fully stir for 3~5 minutes before construction. It needs to be used within 50 minutes.
4. The product can be used for about 30 minutes at 25°C. Please determine the amount of ingredients each time according to the actual temperature and construction progress. The prepared materials must be used up at one time, and the remaining A/B components Must be kept tightly sealed.
5. On-site cleaning and maintenance, floor maintenance
A. After finishing the topcoat, remove the relevant construction materials and tools from the site, and seal it tightly to protect the finished finish.
B. People are allowed to enter and walk after at least 72 hours. Sediment and other garbage items are not allowed.
C. It generally takes 7 days for the paint film to fully cure, during which other engineering construction, handling and installation should be avoided.

Epoxy,flat,coating
Related News
2025
05-31
Application Cases of Epoxy Zinc-Rich Primer on Offshore Platforms
2025
05-21
Choose a suitable epoxy zinc-rich primer to ensure quality and effect.
2025
05-08
How does epoxy zinc-rich primer improve the durability of bridges?
2025
04-28
Differences between epoxy zinc-rich primer and other anti-corrosion coatings
2025
02-21
Advantages of polyurethane waterproof coatings: durability and environmental friendliness
2025
02-06
How to choose a polyurethane waterproof coating that meets your needs?